Walloon authorities ordered Google to suspend construction at its Farciennes data centre after inspectors identified a three-hectare building they said lacked proper planning permission. Google says work is paused while it awaits further guidance; a court hearing over the company’s challenge to a refused water-cooling permit is scheduled for January.
Regional authorities in Wallonia, Belgium, have ordered Google to suspend construction at its planned Farciennes data centre, saying a three-hectare building was erected without proper planning permission. Google says work is paused while it awaits additional guidance, as a separate court challenge over the site’s proposed water-cooling system is due to be heard in January.
Get the latest gadgets delivered free with Prime
- Fast, free delivery on millions of items
- Prime Video, Amazon Music and more included
- Member-only deals all year
A Walloon official told AFP that inspectors visited the site on Thursday and instructed Google representatives to stop construction. Nicolas Yernaux, a spokesman for the regional authorities, described the construction as a “major offense” and said the building covered three hectares. The reports do not include a copy of the order itself; its terms are reported through statements by the authorities.
The dispute also concerns a proposed change to the site’s cooling plan. Belgian media, as cited by AFP, reported that the original project planned to use air cooling. Google later applied to use water from the nearby River Sambre. Regional officials refused that application over the summer, after a dry spring raised concerns about drawing water from the river, AFP reported. Google has challenged the refusal in court.
Google told the BBC it had paused work in Farciennes “pending additional guidance” and said it was committed to complying with local laws. Greenpeace Belgium said in a report this week that drone footage showed construction continuing, and argued that the latest planning permission had been revoked in August. Those statements are claims by Greenpeace; the regional authorities’ reported stop-work order followed an inspection.

Water Permits Shape Data Centre Plans
The order puts a local planning dispute at the centre of a wider question for AI infrastructure: where new computing capacity can be built, and what resources it may use. Data centres house computers that run online services and AI models. Their equipment produces heat, so operators must plan for cooling alongside land, electricity and construction approvals.
In Farciennes, the proposed switch from air cooling to water from the Sambre brought the project into conflict with regional officials during a period of drought concern. The reports do not state how much water Google’s proposed system would use or how it would affect the river. The refusal and the subsequent construction order show that permission for one part of a project does not necessarily settle later changes or construction activity.
For local residents, the case raises questions about oversight of a large development and the use of nearby resources. For cloud and AI customers, it is a reminder that new data centre capacity depends on projects receiving and retaining local approvals. The reporting does not establish that this dispute will affect Google services or customers; any effect on the site’s schedule or capacity remains unknown.
Products Worth Considering

DJI Osmo Mobile 7P 3-Axis Smartphone Gimbal with Mic Mini Transmitter, Infinity Black

Apple AirPods Pro 3 Wireless Earbuds with Active Noise Cancellation

Jackery Explorer 300 Portable Power Station, 292Wh
As an affiliate, we earn on qualifying purchases.
From Cooling Request to Inspection
The Farciennes facility is planned on a former mining site in southern Belgium. The source material describes that site as roughly 50 hectares and identifies the building at issue as three hectares. These figures describe the reported site and disputed building; they do not establish the total planned capacity of the data centre.
The sequence reported is that Google proposed air cooling, then applied to change the plan to river-water cooling. Walloon authorities refused the change over the summer. Google challenged that decision in court, with a hearing scheduled for January. Separately, inspectors visited the site on Thursday and issued instructions to halt construction, according to regional authorities. AFP reported the order on November 27, and the BBC reported Google’s response on November 29, 2026.
The dispute is not the only reported interruption to Google data centre construction in Europe. AFP reported that Finnish authorities halted work at two Google data centre sites in October. The available source material gives no further details about those sites, and the Finnish cases do not establish that the circumstances are the same as in Farciennes.
““Pending additional guidance.””
— Google, in a statement reported by the BBC
Permit Status and Water Use
The stop-work order itself was not available in the source material, so its full terms, scope and any deadline for compliance could not be confirmed. The reports relay the authorities’ explanation through an official’s statements. It is also unclear whether the disputed building can receive approval later, what remedy Google may pursue over the construction finding, or how long work will remain paused.
The sources do not give the proposed water withdrawal, the cooling system’s technical details, or the regional authority’s full reasoning for refusing the change. Greenpeace said the latest planning permission had been revoked in August and reported that work continued, but the material does not independently verify the group’s footage or establish precisely what permissions applied to each part of the project. Google’s court challenge concerns the refused cooling change; the reports do not say whether that case will resolve the separate construction allegation.
January Court Hearing Ahead
The next reported milestone is a court hearing in January on Google’s challenge to Wallonia’s refusal of the water-cooling permit change. The result could clarify whether the proposed river-water system can proceed, but the available reports do not say whether the hearing will address the stop-work order or the building’s planning status.
For now, Google says construction is paused pending further guidance, and regional authorities have ordered work to stop. Further information from the authorities, a copy of the order, or statements from the court could clarify the scope of the restrictions and the project’s path forward.
Key Questions
A regional spokesman told AFP that inspectors identified a three-hectare building constructed without proper planning permission. He called it a “major offense.” The order itself was not available in the source material.
What is the dispute about the River Sambre?
Google applied to change the planned cooling system from air cooling to one using water from the nearby River Sambre. Regional officials refused the request over the summer, with drought concerns reported as part of the dispute. Google has challenged that refusal in court.
Has Google stopped work at the site?
Google told the BBC that it had paused work pending additional guidance. Regional authorities also said inspectors instructed the company to halt construction. Greenpeace had claimed that work was continuing before the reported order.
When will the court consider Google’s challenge?
A hearing is scheduled for January. The reports do not specify a date or say whether the case will also address the separate allegation about construction without proper permission.